Free sample

Sample dossier: FRA03, Frankfurt

What a €490 project dossier contains, shown in full for one real project. Every fact below comes from the permit of 10 September 2025 and carries its page in the PDF.

The project in short

Project
FRA03 data centre, Otto-Horn-Straße, south of Industriepark Höchst, Frankfurt am Main.
Applicant named in the permit
Esfandyar Ventures One SARL.
Authority
Regierungspräsidium Darmstadt.
Decision
Emissions permit under the Federal Immission Control Act (BImSchG), 10 September 2025, 60 pages.

What the permit says, page by page

FactValue in the permitPage
Generator sets60 diesel generator sets: 59 for the data halls, 1 for life safety2
Thermal input392 MW in total, at most2
Engine makeStill open: MTU 20V4000 G74F, CAT 175-16, CAT 3516E or Kohler KD31002
Life-safety engineMTU 18V2000 G26F or CAT 3412C-C182
Exhaust treatmentSelective catalytic reduction (SCR) on every engine2
Urea storage2 tanks of 40 m³, plus a 1.5 m³ day tank on each engine2
Fuel storage20 underground tanks of 100 m³ (2,000 m³), plus a 0.8 m³ day tank on each engine2
Named tank equipmentEurovac NV leak detectors and Vegaswing 51 level switches, or equivalent3
Stacks16 collective stacks, 42 m above ground2, 14
Running hoursAt most 300 hours a year12
Emission limitsNOx 0.5 g/m³ for the main engines; CO from 170 to 500 mg/m³ depending on the make15
Emission measurementsAt every stack, by a body notified under § 29b BImSchG14, 16, 17
Air and noise studiesTÜV Rheinland: air quality forecast of 12 June 2024, noise forecast of 24 August 202311, 19
Permit clockThe permit lapses if construction has not started within two years after it became final6

What it means for a supplier

Engine makers
Four makes are still allowed for 59 engines: the order is still to be won.
Fuel and urea suppliers
A first fill of up to 2,000 m³ of diesel and 80 m³ of urea in storage.
Investors and builders
The two-year clock tells you when the project must show a construction site.

Ownership and level of evidence

Named in the permit
Esfandyar Ventures One SARL, as applicant: the permit is addressed to it.
Linked to CloudHQ
Market listings place CloudHQ's FRA03 at the same street (datacenterHawk). Level of evidence: indirect, the same site name and street; the company-register link is checked for each order.

The source document

Permit of 10 September 2025, still online at the authority on 10 November 2026; a copy is kept in our archive with its SHA-256 fingerprint.

Open the permit (PDF, German)

Order a dossier for another project

Any project in the atlas, documented the same way: dated filings, the fleet down to the engine model when the filing gives it, ownership with its level of evidence, every fact cited to its page. €490 per project, €2,900 for ten.

Order a dossier