Environmental permit granted
Equinix (Sweden) AB data centre in Stockholm, Sweden
Latest document dated 8 Jun 2023, from Naturvårdsverket. Official document
- backup generators
- 16
- MW of generator thermal input
- 88.3
The backup fleet in the filing
Timeline
Public documents for this project, and what our daily checks found.
- Environmental permit granted
Naturvårdsverket. Official document
- Licence Display windows, objection deadlines and every amendment, with page references
The record
Standby Atlas recordSE-AB-STOCKHOLM-EQUINIX-SK2
- Location
- Stockholm (Förbrännaren 10), Sweden
- Operator or project company
- Equinix (Sweden) AB
- Stage
- Environmental permit granted
- Filing date
- 8 Jun 2023
- IT load
- Not stated in the filing
- Grid connection
- Not stated in the filing
- Backup generators
- 16
- Generator thermal input
- 88.3 MW
- Engine makes named
- Not named in the filing
Source: Naturvårdsverket. Checked on 9 November 2026.
What the licences add for this project
Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.
Other projects in Sweden
- 280generatorsEcoDC 2 AB (EcoDataCenter) data centre in Borlänge, SwedenEnvironmental permit granted, 12 May 2026
- 145generatorsatNorth AB data centre in Sollefteå, SwedenPre-application consultation, 16 Jun 2026
- 40generatorsEcoDC Östersund AB data centre in Östersund, SwedenEnvironmental permit granted, 23 Jun 2025
- 12generatorsatNorth AB data centre in Stockholm, SwedenPre-application consultation, 14 Jan 2026
- —generatorsDigital Realty AB data centre in Stockholm, SwedenEnvironmental permit application, 26 Nov 2025
- 20generatorsSI STO 01.2 AB data centre in Upplands Väsby, SwedenEnvironmental permit granted, 11 May 2023